Standard Crystal Report - Job Detail Report
Issue/Symptom/Question
Standard Crystal Report - Job Detail Report
Applies To
Penta for Windows
Crystal Report - Job Detail Report
Resolution/Fix/Answer
Use the Job Detail report to manage cost on a job. The report displays Costcode level cost information, as well summary job financial information including contract, accounts receivable, cash flow, and gross margin.
Report Code: jc_jobDtl_p62_cr11.rpt
Available Parameters:
Example Report Results:Â
Report Fields
Code -Â ID of the Costcode.
Type -Â ID of the Cost Type associated with the Costcode.
Descr - The Costcode’s description.
Job Estimate Units - The Costcode’s estimated number of units.
UOM -Â The unit of measure associated with the Costcode.
Job Estimate Hours -Â Estimated hours for the Costcode.
Unit Cost -Â Estimated unit cost for the Costcode.
Job Estimate Cost -Â Estimated cost for the Costcode.
Commitments -Â Total value of subcontract and purchase order commitments.
Hours - Current period’s number of hours for the Costcode, based on the report date range.
Cost - The current period’s Cost for the Costcode, based on the report date range.
Cumulative Totals Hours -Â Job to date hours for the Costcode.
Cumulative Totals Cost -Â Job to date cost incurred for the Costcode.
Cumulative Units -Â Job to date units for the Costcode.
Cumulative Unit Cost -Â Total amount of Unit Cost for the Costcode.
Projected %Cmpl/Date Set -Â The entered percent complete for the Costcode and the date of the percent complete.
Projected $ at Complete -Â The forecast cost at completion for the Costcode.
Variance - Calculated as: Job Estimate Cost – Projected $ at Complete