Standard Crystal Report - Job Cost and Productivity
Issue/Symptom/Question
Standard Crystal Report - Job Cost and Productivity
Applies To
Penta for Windows
Crystal Report - Job Cost and Productivity
Project Management
Resolution/Fix/Answer
Use the Job Cost and Productivity report to review job cost, revenue, and Costcode performance. At the end of each job, the report shows a Cost Summary and a revenue summary.
Report Code: jc_jobCostAndProd_p80_cr11.rpt
Available Parameters:
Example Report Results:
Report Fields
Costcode - ID of the Costcode.
CT - ID of the Cost Type.
Description - The Costcode’s description.
UOM - The Costcode’s Unit of Measure.
Estimate Original - The Costcode’s original estimate.
Estimate Current - The Costcode’s current estimate including approved change requests.
Committed Total - The total amount of purchase order and subcontract committed costs for the Costcode.
Committed remaining - The purchase order and subcontract committed cost not yet invoiced.
Actual Current - The Costcode’s actual cost amount incurred during the report date range.
Actual PF Job-to-Date - Calculated as: (Job to date units ÷ Job to date hours) ÷ (Current estimated units ÷ Current estimated hours)
Actual PF - Calculated as: (Current units ÷ Current hours) ÷ (Current estimated units ÷ Current estimated hours)
Forecast to Complete - The forecast cost to complete the work on the Costcode.
Forecast to Complete PF - Calculated as: (Forecast at complete units – Job to date units) ÷ (Current estimated units ÷ Current estimated hours)
Forecast At complete - The forecast cost at complete for the Costcode.
Forecast at Complete PF - Calculated as: (Forecast at complete units ÷ Forecast at complete hours) ÷ (Current estimated units ÷ Current estimated hours)
Variance - Calculated as: Forecasted amount – Actual cost
Cost Summary Fields - This section provides a summary of cost on the job at a Cost Type level. Information includes estimate, actual, and forecasts.
Cost Type - ID of the Cost Type.
Original Estimate - The Cost Type’s original estimate.
Approved Changes - The amount of approved estimate changes for the Cost Type.
Current Estimates - The original estimate +/- the approved changes.
Pending Changes - Estimate changes for the Cost Type that are not yet approved.
Actual Current Cost - Actual costs for the Cost Type charged to the job in the current period.
JTD Cost - Job to date cost for the Cost Type.
% Spent - Calculated as: Job to date cost ÷ Current estimate.
Forecast Cost To Complete - Forecasted costs remaining to complete work for the Cost Type.
Forecast Cost At Complete - Forecast cost at completion of work for the Cost Type.
Projected Variance - Calculated as: The forecasted cost at complete – The current estimate
Revenue Summary Fields - This section provides a summary of revenue related information for the job, including contract, billings, revenue, gross margin, and over/under billings
Original Contract - The original contract amount for the job.
Approved Changes - Approved changes to the job’s contract amount.
Current Contract - Calculated as: Original contract + Approved changes
Pending Changes - Pending changes to the job contract amount.
Projected Contract - Calculated as: Current contract + Pending changes
Billings to Date - Job to date billing amount.
Projected Remaining Billings - Calculated as: Projected contract – Billings to date
Earned Revenue - The Job to date earned revenue amount.
(Over)/Under Billed - The Job’s (over)/under billed balance.
Gross Margin - Original - Calculated as: Original contract – Original estimate.
Gross Margin - Current - Calculated as: Current contract – Current estimate
Gross Margin - Actual - Calculated as: Earned revenue – Job to date cost
Gross Margin - Projected - Calculated as: Projected Contract – Cost at complete
Gross Margin – Indicated Outcome - Calculated as: Current Contract – Cost at complete