Standard Crystal Report - Job Summary with Financial

Issue/Symptom/Question

Standard Crystal Report - Job Summary with Financial

Applies To

Penta for Windows

Crystal Report - Job Summary with Financial

Project Management

Resolution/Fix/Answer

Use this report to review the financial status of a job. The report includes cost estimates, actual costs, and projected costs. In addition, you can view the current status for the contract, receivables, cash flow, and project.

Report Code: jc_jobSmyByCtFinc_p90_cr11.rpt

Available Parameters:

Example Report Results: 

Fields

Cost Type Category - List of Cost Type categories used on the job.

Original Estimate - The original cost estimate.

Approved CO’s - Amount of estimate changes for approved change orders.

Revised Estimate - The original cost estimate plus any approved change orders.

Period Cost - Actual cost incurred during the report date range.

Cost To Date - The Job’s to-date cost.

Remaining Committed - The amount of purchase order and subcontract commitments not yet invoiced by the vendor/subcontractor.

Project’d Cost To Complete - Forecast cost to complete.

Project’d Cost At Complete - Forecast cost at completion.

Variance - Calculated as: Revised Estimate – Project’d Cost at Complete

Contract Status box - This box provides the a recap of the contract amounts, including original contract, approved change orders, the revised contract amount, and the amount of any pending change orders.

Receivable Status box - This box provides a recap of receivables and receipts, including gross billings, retention withheld, net billing to date, amount due, and received payments.

Cash Flow Status box - This box provides a recap of disbursements and cash position, including cost to date, net payables, AP retention, cash disbursed, and the job’s overall cash position.

Project Status box - The box provides various information on the job as of the date you ran the report for. It includes information such as the Last Day of Work, % Complete, Estimated Gross Profit, Projected Gross Profit, % Labor Complete, and % Projected Gross Margin.