Standard Crystal Report - Cost Type Category Totals By Job


Standard Crystal Report - Cost Type Category Totals By Job

Issue/Symptom/Question

Standard Crystal Report - Cost Type Category Totals By Job

Applies To

Penta for Windows

Crystal Report - Cost Type Category Totals By Job

Project Management

Resolution/Fix/Answer

Use the Job Cost Type Category by Costcode report to review the status of a job or jobs within an organizational unit. The report provides a summary of the contract information including:

  • Current contract amount
  • Billed to date
  • Collected to date
  • Retention held
  • Outstanding receivable

Job cost information is summarized by Cost Type category (Labor, Burden, Equipment, Materials, Subcontracts, and Other) and includes the following values:

  • Original Estimate
  • Estimate Approved Change Requests
  • Current Estimate
  • Month-to-Date Cost
  • Job-to-Date Cost
  • Budget Variance

This report shows totals by Job, OU ID, and report grand total.

Report Code: md_jobCostTypeCatByJob_p65_cr11.rpt

Available Parameters:

Example Report Results:

Report Fields

Current Contract Amount - Calculated as: The original contract value + Approved contract changes

Billed To Date - The job to date billed.

Collected To Date - Total cash receipts collected to date on billings for the job.

Retention Held - The amount of open accounts receivable retention for the job.

Outstanding Receivable - Open receivables already billed but not yet collected for the job.

Original Estimate - Original estimated cost.

Estimate Change Requests - Approved changes to the estimated cost.

Current Estimate - Calculated as: Original estimate + Approved estimate changes

MTD Cost - The month-to-date cost recorded for the job.

JTD Cost - The total costs recorded to date for the job.

Budget Variance - Calculated as: Current Estimate – JTD Cost