Standard Crystal Report - Cost Type Category Totals By Job
Issue/Symptom/Question
Standard Crystal Report - Cost Type Category Totals By Job
Applies To
Penta for Windows
Crystal Report - Cost Type Category Totals By Job
Project Management
Resolution/Fix/Answer
Use the Job Cost Type Category by Costcode report to review the status of a job or jobs within an organizational unit. The report provides a summary of the contract information including:
Current contract amount
Billed to date
Collected to date
Retention held
Outstanding receivable
Job cost information is summarized by Cost Type category (Labor, Burden, Equipment, Materials, Subcontracts, and Other) and includes the following values:
Original Estimate
Estimate Approved Change Requests
Current Estimate
Month-to-Date Cost
Job-to-Date Cost
Budget Variance
This report shows totals by Job, OU ID, and report grand total.
Report Code: md_jobCostTypeCatByJob_p65_cr11.rpt
Available Parameters:
Example Report Results:
Report Fields
Current Contract Amount - Calculated as: The original contract value + Approved contract changes
Billed To Date - The job to date billed.
Collected To Date - Total cash receipts collected to date on billings for the job.
Retention Held - The amount of open accounts receivable retention for the job.
Outstanding Receivable - Open receivables already billed but not yet collected for the job.
Original Estimate - Original estimated cost.
Estimate Change Requests - Approved changes to the estimated cost.
Current Estimate - Calculated as: Original estimate + Approved estimate changes
MTD Cost - The month-to-date cost recorded for the job.
JTD Cost - The total costs recorded to date for the job.
Budget Variance - Calculated as: Current Estimate – JTD Cost