How To use Production Units in TEP

Issue/Symptom/Question

We are looking to use production units in the TEP app, how can we start?

Applies To

TEP 

Costcode Estimate Entry

Resolution/Fix/Answer



Setup
Set up Unit Estimates at the Costcode Level (using the “Current Cost units” column in the Costcode and Estimate Entry Screen)
Project Management> Estimates> Costcode and Estimate Entry


Entry


Create an activity Log, including the Jobs/Costcodes for which you plan on tracking Production Units


 



Processing


Submit and approve the activity Log. Distributed units can be viewed via various Workbench reports.