Unable to view cost types/costcodes on Production tab in TEP


Unable to view cost types/costcodes on Production tab in TEP

Issue/Symptom/Question

When attempting to enter Production Units for a Job in TEP, the Production Units tab isn't showing the costcodes that I need to enter production units for.

Applies To

PENTA for Windows

Project Management > Setup > Cost Types

TEP Application

Resolution/Fix/Answer

1. Ensure the costcodes are setup on the project

2. Ensure the cost type is assigned a cost type category of either Equipment or Labor. Only cost types that have a cost type category of equipment or labor, will be accessible on the Production tab in TEP
 