Unable to view cost types/costcodes on Production tab in TEP
Issue/Symptom/Question
When attempting to enter Production Units for a Job in TEP, the Production Units tab isn't showing the costcodes that I need to enter production units for.
Applies To
PENTA for Windows
Project Management > Setup > Cost Types
TEP Application
Resolution/Fix/Answer
1. Ensure the costcodes are setup on the project
2. Ensure the cost type is assigned a cost type category of either Equipment or Labor. Only cost types that have a cost type category of equipment or labor, will be accessible on the Production tab in TEP