Defaulting Equipment from Crew to TEP Activity Log
Defaulting Equipment from Crew to TEP Activity Log
Issue/Symptom/Question
Equipment is linked to a Crew, but when the Crew is assigned to the Activity Log in TEP, the Equipment does not default, why?
Applies To
PENTA TEP
Crew Maintenance
Equipment Usage
Resolution/Fix/Answer
Prerequisites to default EQ to the EQ Usage section of the Activity Log from a Crew
- The Equipment is assigned to an Active Crew (Payroll > Employees > Other Employee Attributes)
- The Equipment Asset Class is set to be included on TEP (Project Management > Work Package Manager > WPM Configuration > Asset Classes Tab)
- The Equipment/Fixed Asset has a Charging by Usage entry (Fixed Asset Management > Asset Information > Charging by Usage Tab)
, multiple selections available,
Related content
Employee not available to add to activity log in TEP
Employee not available to add to activity log in TEP
More like this
Criteria for Adding Resource Types to Equipment Added to Maintenance Contracts by Technicians
Criteria for Adding Resource Types to Equipment Added to Maintenance Contracts by Technicians
More like this
Equipment Timecard Interface batch not distributing
Equipment Timecard Interface batch not distributing
More like this
How to link piece of equipment to an equipment charge schedule?
How to link piece of equipment to an equipment charge schedule?
More like this
Error entering time in TEP
Error entering time in TEP
More like this
Set up tools in MFS so that technicians can charge them to Work Order tickets
Set up tools in MFS so that technicians can charge them to Work Order tickets
More like this