Can we create Subcontracts for Overhead?
Issue/Symptom/Question
Where can we enter Subcontracts that are Overhead?
Can we charge a subcontract to overhead in PENTA?
Is there any way to charge a Subcontract to a non job distribution type in PENTA?
Applies To
Subcontract Information
Project Management> Committed Costs> Subcontracts
Purchase Order Grid Option
Project Management> Committed Costs> Subcontracts
Resolution/Fix/Answer
There is currently no way to facilitate an Overhead or "Non-Job" Subcontract using the Subcontract module in Penta.
Instead of the Subcontract modules, simply use a PO to record "Non-Job" subcontracts.