Can we create Subcontracts for Overhead?
Can we create Subcontracts for Overhead?
Issue/Symptom/Question
Where can we enter Subcontracts that are Overhead?
Can we charge a subcontract to overhead in PENTA?
Is there any way to charge a Subcontract to a non job distribution type in PENTA?
Applies To
Subcontract Information
Project Management> Committed Costs> Subcontracts
Purchase Order Grid Option
Project Management> Committed Costs> Subcontracts
Resolution/Fix/Answer
There is currently no way to facilitate an Overhead or "Non-Job" Subcontract using the Subcontract module in Penta.
Instead of the Subcontract modules, simply use a PO to record "Non-Job" subcontracts.
, multiple selections available,
Related content
Subcontracts
Subcontracts
More like this
Subcontract Transactions for Work Orders
Subcontract Transactions for Work Orders
More like this
Can PENTA automatically close (100% Complete) Subcontracts?
Can PENTA automatically close (100% Complete) Subcontracts?
More like this
Is there a way to restrict the cost type charged on Sub Contracts?
Is there a way to restrict the cost type charged on Sub Contracts?
More like this
Overhead Distribution Rule Information
Overhead Distribution Rule Information
More like this
Intercompany System option definitions
Intercompany System option definitions
More like this