Can PENTA automatically close (100% Complete) Subcontracts?
Can PENTA automatically close (100% Complete) Subcontracts?
Issue/Symptom/Question
Can PENTA automatically close Subcontracts?
How does one "close" a subcontract"
Applies To
- PENTA for Windows
- Project Management > Committed Costs > Subcontracts
- System Management > System Rules > System Configuration
Resolution/Fix/Answer
When a Subcontract goes to a 100% Complete status the Subcontract is closed.
In System Configuration on the Project Management tab, a user can mark N/Y if they want all Subcontracts to Automatically close when the total amount is booked.
, multiple selections available,
Related content
Can we create Subcontracts for Overhead?
Can we create Subcontracts for Overhead?
More like this
Subcontracts
Subcontracts
More like this
Subcontract Default Status
Subcontract Default Status
More like this
Contract Completion - Billing Purposes
Contract Completion - Billing Purposes
More like this
Is there a way to restrict the cost type charged on Sub Contracts?
Is there a way to restrict the cost type charged on Sub Contracts?
More like this
Update Work Order Status When Associated Maintenance Contract Is Invoiced
Update Work Order Status When Associated Maintenance Contract Is Invoiced
More like this