Can PENTA automatically close (100% Complete) Subcontracts?
Issue/Symptom/Question
Can PENTA automatically close Subcontracts?
How does one "close" a subcontract"
Applies To
- PENTA for Windows
- Project Management > Committed Costs > Subcontracts
- System Management > System Rules > System Configuration
Resolution/Fix/Answer
When a Subcontract goes to a 100% Complete status the Subcontract is closed.
In System Configuration on the Project Management tab, a user can mark N/Y if they want all Subcontracts to Automatically close when the total amount is booked.