Subcontract Default Status
Issue/Symptom/Question
Can we have the status on a subcontract default to pending when a subcontract is initially setup?
Applies To
Project Management > Committed Costs > Subcontracts
Accounts Payable > Setup > Hold Information > Automated Hold Reasons
Resolution/Fix/Answer
PENTA defaults the subcontract status based on your usage of the 'Subcontract Status Is Pending' hold reason within the Accounts Payable module:
- If you are using the ''Subcontract Status Is Pending'Â hold reason, PENTA defaults the Subcontract status as 'Pending'.
- If using this hold reason, PENTA will place any SC-related AP invoices on hold until the PO status has been updated to Active at which point the hold is released.
- If you are not using the ''Subcontract Status Is Pending' hold reason, PENTA defaults the Subcontract status as 'Active'.