Changes not Saving to Schedule of Values
Changes not Saving to Schedule of Values
Issue/Symptom/Question
The values are not holding in the Schedule of Values window, so our contract amount is showing up incorrectly.
We create the line items with descriptions and amounts before exiting the window. When we go back in, the amounts are gone.
Applies To
Project Management > Owner Contract Information > Schedule of Values
PENTA for Windows
Resolution/Fix/Answer
- Open Schedule of Values (Project Management > Owner Contract Information > Schedule of Values) Window
- Create new line with Line Item Number, Line Item Type, Description, and Amount
- Click anywhere outside of the Amount field, click the "X" to close the window.
Cause
Clicking outside of the Amount field then closing the window saves any changes that have been made within this window to the database.
, multiple selections available,
Related content
Unable to enter Line Item number in Schedule of Values window
Unable to enter Line Item number in Schedule of Values window
More like this
Why am I unable to see a line item in the Schedule of Values window?
Why am I unable to see a line item in the Schedule of Values window?
More like this
Why isn't the correct Contract amount showing in the Contract Completion billing Purposes Screen?
Why isn't the correct Contract amount showing in the Contract Completion billing Purposes Screen?
More like this
Schedule of Values
Schedule of Values
More like this
Field Entry Required for "Sales Account"
Field Entry Required for "Sales Account"
More like this
Project Review and Forecast Entry (PRFE) screen - Commitments Do Not Match
Project Review and Forecast Entry (PRFE) screen - Commitments Do Not Match
More like this