Changes not Saving to Schedule of Values

Issue/Symptom/Question

The values are not holding in the Schedule of Values window, so our contract amount is showing up incorrectly. 

We create the line items with descriptions and amounts before exiting the window. When we go back in, the amounts are gone.

Applies To

Project Management > Owner Contract Information > Schedule of Values

PENTA for Windows

Resolution/Fix/Answer


  1. Open Schedule of Values (Project Management > Owner Contract Information > Schedule of Values) Window
  2. Create new line with Line Item Number, Line Item Type, Description, and Amount
  3. Click anywhere outside of the Amount field, click the "X" to close the window.

Cause

Clicking outside of the Amount field then closing the window saves any changes that have been made within this window to the database.