Subcontract Change Orders

Overview:

A Subcontract Change Order is change to an already established Subcontract Agreement, typically between the primary contractor on a Job, and an independent third party. After creating/linking a Subcontract Change Order, a separate Subcontract Change Order document is typically generated in PENTA, and sent to the Subcontractor for authorization/signature. 

Benefits:

  • Used to get sign-off/approval for extra work
  • Track original vs Subcontract changes

Roles:

  • Project Administrator
  • Project Manager

Location:

  • Project Management > Committed Costs > Subcontracts

Video: