Issue/Symptom/Question
Why does the estimate import process not work? Why does an internal system error show when uploading an estimate?
Applies To
PENTA for Windows > Project Management > Estimates > Estimate Worksheet
Microsoft Excel
Resolution/Fix/Answer
There could be a number of reasons why the import fails, here are some of the more frequent reasons:
- The Job already exists on the batch trying to import to
- Delete the Job form the middle section of the screen and then put focus next to the Job again and import
- Delete the Job form the middle section of the screen and then put focus next to the Job again and import
- The field labels have been removed or are incorrect from the Excel File
- See the PENTA Reference Manual (available on Help drop down on Menu bar) for information on field labels (Project Management > Window Descriptions > Estimate Worksheet Import)
- Make sure the start_detail label identifies the first Costcode row to load
- Highlight the first row and type in start_detail then hit Enter key to lock in the field label
- Highlight the first row and type in start_detail then hit Enter key to lock in the field label
- The Excel file is opened
- Always Save and Close the Excel file prior to import
- Always Save and Close the Excel file prior to import
- Duplicate Field Labels exist
- Open the Name Manager
- Delete all existence of the duplicate labels and then add back the label in the correct cell, column, or row
- Open the Name Manager
- Confirm the Date field is in the Date Format