Jira Legacy
serverPenta Technologies
serverId9a8cfe53-2fe8-3fdc-8519-0c9ade9af727
keySUPPORT-117

Issue/Symptom/Question

  • User was in the middle of entering a batch when PENTA went down
  • When the user got back into PENTA and queried back the batch the hours in the users columns were missing
  • Any new hours the user entered were showing but previous hours not showing up

Environment

Function: Entering hours in a weekly batch in the Payroll Time/Equipment/Production window

Product: Core PENTA

Module: Payroll

Applies To

Payroll (PR)

PENTA for Windows > Payroll > Time Entry >Time Equipment Production Units Entry Window

The User has a specific saved Grid layout

User had an internet issue connecting to the remote desktop

Resolution/Fix/Answer

  1. Select Weekly as batch entry type
  2. Enter the Period End date
  3. Check the Show columns for Reg, Prem 1, and Prem 2 Hrs box
    Image Added
  4. Click on the Weekly tab
  5. Now hours are split into Reg, Prem 1, and Prem 2 columns

...