How do I view previous forecasts performed on a job?


How do I view previous forecasts performed on a job?

Issue/Symptom/Question

Is there a way to see the previous forecasts performed on a job? We would like to review historical job data for comparison and use it for future jobs.

Environment

PENTA for Windows

Project Management 

Project Review & Forecast Entry

Resolution/Fix/Answer

1) Project Management > Inquires > Project Review & Forecast Entry

2) For "Low Value" enter "Job ID" and click "Ok"

3) Pop-up window will appear for saving the query, click "No"

4) Left hand side you will see "Job ID", click on the "+" to open up the folder

5) Click once on "Job ID Job Name

6) Place your cursor over the "Cost" number for "Forecast at Completion" and click once

7) A "Forecast and Completion History" table will open, displaying the history of the forecast for that job