How do I view previous forecasts performed on a job?
How do I view previous forecasts performed on a job?
Issue/Symptom/Question
Is there a way to see the previous forecasts performed on a job? We would like to review historical job data for comparison and use it for future jobs.
Environment
PENTA for Windows
Project Management
Project Review & Forecast Entry
Resolution/Fix/Answer
1) Project Management > Inquires > Project Review & Forecast Entry
2) For "Low Value" enter "Job ID" and click "Ok"
3) Pop-up window will appear for saving the query, click "No"
4) Left hand side you will see "Job ID", click on the "+" to open up the folder
5) Click once on "Job ID Job Name"
6) Place your cursor over the "Cost" number for "Forecast at Completion" and click once
7) A "Forecast and Completion History" table will open, displaying the history of the forecast for that job