In the Change Request Type window what does the Must Zero Balance checkbox mean?
In the Change Request Type window what does the Must Zero Balance checkbox mean?
Issue/Symptom/Question
- In the Change Request Type window what does the Must Zero Balance checkbox mean?
- What is an example of a Change Request Type that might use this Must Zero Balance?
Applies To
Change Request Configuration
Project Management > Change Management > Change Request Type window
Resolution/Fix/Answer
- Must Zero Balance checkbox means that the transfer of costs must be in balance
- This is used for budget shifts - transferring estimate amounts from one costcode to another costcode where the total costs of the existing Estimate does not change as a result of this Change Request
, multiple selections available,