Workbench panel PM: Job Cost - Cost Summary Report not calculating Projected Variance
Issue/Symptom/Question
We recently upgraded our Workbench version and now PM: Job Workbench - PM: Job Cost - Cost Summary Report is not calculating Projected Variance - Labor Hours or Projected Variance - Cost. This worked in the past; and they are not calculating on any users for any jobs.
Applies To
PENTA Workbench
PM: Job Workbench > PM: Job Cost > Cost Summary Report
Resolution/Fix/Answer
When a Workbench upgrade is completed, any default layouts do not automatically update if column changes are made. The default layouts have to be recreated.
Cause
Users created default layouts for the Workbench reports.