Standard Crystal Report - Job Summary Report
Issue/Symptom/Question
Standard Crystal Report - Job Summary Report
Applies To
Penta for Windows
Crystal Report - Job Summary Report
Resolution/Fix/Answer
Use the Job Summary report to identify jobs that have a projected cost variance. This report shows one line per job.
Report Code: jc_jobSmy_p62_cr11.rpt
Available Parameters:
Example Report Results:
Fields
Job ID - ID of the Job.
Job Name - Name of the Job.
Contract + Approved Chg - Contract amount plus any approved change orders as of the report through date.
Pending Change Orders - Dollar amount of the Job’s pending contract change orders.
Estimated Costs - Total amount of the Job’s estimated costs.
Costs This Period - Total amount of costs incurred in the report date range.
Costs To Date - The Job’s to-date cost.
Percent Complete - Calculated as: Cost to Date ÷ Projected Costs
Remaining Costs - The forecast cost to complete for the job.
Projected Costs - The forecast cost at complete for the job.
Variance - Calculated as: Estimated Costs – Projected Costs