Standard Crystal Report - Labor Feedback - Analysis
Issue/Symptom/Question
Standard Crystal Report - Labor Feedback - Analysis
Applies To
Penta for Windows
Crystal Report - Labor Feedback - Analysis
Project Management
Resolution/Fix/Answer
For each Job included, this report lists the estimated and actual hours, broken down by Cost Type and then Costcode. This report has two sections:
- Labor Feedback – Analysis: For each Costcode, this section shows the original estimated hours, change order hours, hours expended through the period end date, and estimated hours remaining.
- Labor Feedback – Change Order Hours: This section shows the detail behind each change order, listed by Costcode. Totals are provided for all Costcodes relating to the job.
Report Code: jc_jobLbrFdbk_p80_cr11.rpt
Available Parameters:
Report Results:
Report Fields
Costcode - ID of the Costcode.
Costcode Description - Description of the Costcode.
Estimate Description - Description assigned to the Costcode estimate.
Original Estimate Hours - Original estimated hours for the Costcode.
Change Order Hours - Any change in estimated hours from a Change Order. Part 2 of this report has additional detail for each Change Order.
Hours Expended Through (Date) - The total hours charged to the Costcode through the Period End Date you specified when generating the report.
Hours Remaining In Est. - The estimated remaining hours to completion. PENTA calculates this value as: The original estimated hours +/- (Change Order hours – The hours expended through the Period End Date)